Tag: Galloway Hydro Scheme

Historic Tongland Power Station restored following £2 million refurbishment

One of Scotland’s oldest hydroelectric power stations has been given a new lease of life following a £2 million refurbishment by Drax, helping preserve the historic facility for future generations. Tongland Power Station, near Kirkcudbright in Scotland, is part of the Galloway Hydro Scheme which was developed in the 1930s.

The power station is one of six hydroelectric facilities within the Galloway Hydro Scheme, a network of dams, reservoirs and power stations stretching across Dumfries and Galloway. Together they have provided renewable electricity to Scotland for generations.

The project saw the power station’s exterior carefully restored using specialist materials designed to protect and preserve the historic building for decades to come. Special measures to protect the power station during the construction work were put in place, with Tongland designated as a Category A listed building by Historic Environment Scotland due to its importance in the development of hydropower and its “finely detailed modernist classical design”.

In addition to the work to the building’s external façade, Drax has revamped the site’s exhibition space within the main station building to enable the power station to once again host school tours. Further work to the building’s internal paint work will be carried out this year.

Ian Kinnaird, Drax’s FlexGen Assets Director, said: “The Galloway Hydro Scheme has been generating flexible, renewable electricity for 90 years, and this major refurbishment means it will continue to do so for many more years to come.

“This was a complex project, with great care taken by Drax and our contracting partners to protect this historic building during the work. Tongland has been part of Scotland’s energy story for almost a century, so everyone involved should feel incredibly proud to see it looking as good as new.”

The completion of Tongland’s external refurbishment is part of a wider investment in Scotland by Drax. The company is currently installing around 1,500 solar panels across its Galloway and Lanark hydro schemes, completing an £80m upgrade of its iconic ‘Hollow Mountain’ Cruachan Power Station, and work will soon start on an upgrade at its Glenlee site.

ENDS

Media contact

Aidan Kerr
E[email protected]

About Drax

Drax’s purpose is to enable a zero carbon, lower cost energy future. Our strategic aims are to be a UK leader in flexible, renewable generation and a global leader in sustainable biomass pellet production.

Our operations

Drax owns and operates a portfolio of flexible, low-carbon and renewable UK power assets – biomass, hydro, pumped storage and OCGT generation – which provide dispatchable power and system support services to the electricity grid.

We are the UK’s largest source of renewable power by output, and Drax Power Station is the UK’s largest single source of renewable electricity by output.

Through our pellet production facilities in North America, Drax is a leading integrated producer of sustainable biomass.

Drax supplies renewable electricity to UK industrial and commercial customers, offering a range of energy-related services including energy optimisation, as well as electric vehicle strategy and management.

Website: www.drax.com

Capacity Market agreements for existing assets

Engineer below Cruachan Power Station dam

RNS: 3530F
Drax Group plc

(“Drax” or the “Company”; Symbol:DRX)

Drax confirms that it has provisionally secured agreements to provide a total of 2,562MW of capacity (de-rated 2,333MW) from its existing gas, pumped storage and hydro assets(1). The agreements are for the delivery period October 2023 to September 2024, at a price of £15.97/kW(2) and are worth £37 million in that period. These are in addition to existing agreements which extend to September 2023.

Drax did not accept an agreement for the 60MW Combined Cycle Gas Turbine (CCGT) at Blackburn Mill.

A new-build CCGT at Damhead Creek and four new-build Open Cycle Gas Turbine projects participated in the auction but exited above the clearing price and did not accept agreements.

Enquiries:

Drax Investor Relations: Mark Strafford
+44 (0) 7730 763 949

Media:

Drax External Communications: Ali Lewis
+44 (0) 7712 670 888

Website: www.drax.com

Notes:

  1. Existing assets – gas (Damhead Creek, Rye House, Shoreham and three existing small gas turbines at Drax Power Station), Cruachan Pumped Storage and the Galloway hydro scheme (Tongland, Kendoon and Glenlee).
  2. Capacity Market agreements stated in 2018/19 real-terms, with payments indexed to UK CPI.

END

Capacity Market agreements for existing assets and review of coal generation

Drax's Kendoon Power Station, Galloway Hydro Scheme, Scotland

RNS Number : 6536B

T-3 Auction Provisional Results

Drax confirms that it has provisionally secured agreements to provide a total of 2,562MW of capacity (de-rated 2,333MW) from its existing gas, pumped storage and hydro assets(1). The agreements are for the delivery period October 2022 to September 2023, at a price of £6.44/kW(2) and are worth £15 million in that period. These are in addition to existing agreements which extend to September 2022.

Drax did not accept agreements for its two coal units(3) at Drax Power Station or the small Combined Cycle Gas Turbine (CCGT) at Blackburn Mill(4) and will now assess options for these assets, alongside discussions with National Grid, Ofgem and the UK Government.

A new-build CCGT at Damhead Creek and four new-build Open Cycle Gas Turbine projects participated in the auction but exited above the clearing price and did not accept agreements.

T-4 Auction

Drax has prequalified its existing assets(5) and options for the development of new gas generation to participate in the T-4 auction, which takes place in March 2020. The auction covers the delivery period from October 2023.

CCGTs at Drax Power Station

Following confirmation that a Judicial Review will now proceed against the Government, regarding the decision to grant planning approval for new CCGTs at Drax Power Station, Drax does not intend to take a Capacity Market agreement in the forthcoming T-4 auction. This project will not participate in future Capacity Market auctions until the outcome of the Judicial Review is known.

Enquiries:

Drax Investor Relations
Mark Strafford
+44 (0) 7730 763 949

Media:

Drax External Communications
Matt Willey
+44 (0) 0771 137 6087

Photo caption: Drax’s Kendoon Power Station, Galloway Hydro Scheme, Scotland

Website: www.drax.com